Government contract termination: What you need to know
Fair warning. Contract terminations often come loaded with expected and unexpected requirements. Knowing what to do and when to do it can make all the difference. Almost every Federal contract or solicitation contains provisions that allow the Government to terminate the contract, either for convenience or for default, as explained below.
Contract termination is rarely a surprise event. Prior to a termination, many events such as change orders and stop work notifications may warn a contractor of an impending termination. When no other options appear to exist, the CO will discuss the issues and performance concerns with the contractor, providing written notifications and direction in accordance with FAR termination requirements. This information may come in the form of a corrective action plan request, notice of termination for convenience, or similar documentation.
A written notice of termination specifies the extent of the termination and the effective date. These notices often contain both information based on the contractor’s circumstances and the nature of the contractor’s products or services that are being terminated. Also, under a termination of convenience, contractors may find that only portions of the contract have been terminated. Nonetheless, the contractor must comply with the notice and the requirements of the applicable Federal Acquisition Regulation (FAR) termination clause, except as otherwise directed by the Termination Contracting Officer (TCO). Regardless of any delay in determining or adjusting any amounts due to the contractor for work performed, and for any costs incurred prior to issuance of the termination notice, the contractor has a general obligation to:
- Stop work immediately.
The contractor must notify its project team, including suppliers and subcontractors, to stop work immediately on the terminated portion of the contract and stop placing subcontracts thereunder. - Terminate subcontracts, purchase orders, and other agreements.
The contractor must terminate all agreements related to the terminated portion of the contract, preferably through a written notice referencing the flow down clauses and circumstances. - Advise the TCO of any special circumstances.
The contractor must quickly advise the TCO of any special circumstances that would preclude the immediate stoppage of work. - Submit equitable adjustment.
Under the termination clause, after partial termination a contractor may request an equitable adjustment of the price or prices of the continued portion of a fixed-price contract. - Protect and preserve property.
The contractor must take necessary or directed action to protect and preserve property in the contractor’s possession in which the Government has or may acquire an interest. If directed by the TCO, it must deliver the property to the Government. - Notify the TCO of any legal proceedings.
The contractor must promptly notify the TCO in writing of any legal proceedings stemming from any subcontract or other commitment related to the terminated portion of the contract. - Settle outstanding liabilities and proposals arising out of termination of subcontracts.
The contractor must settle outstanding liabilities arising out of termination of subcontracts, obtaining any approvals or ratifications required by the TCO. - Submit a settlement proposal.
The contractor must promptly submit its own settlement proposal, supported by accounting data and appropriate schedules sufficient for adequate review within 365 days of receipt of the termination notice. There are three major Government settlement proposal forms, differing based on the type of terminated contract:- Standard Form (SF) 1435: Settlement Proposal (Inventory Basis) (see FAR 53.249(a)(2))
- SF 1436: Settlement Proposal (Total Cost Basis) (see FAR 53.249(a)(3))
- SF 1438: Settlement Proposal (Short Form) (used when the total charges being proposed are less than $10,000) (see FAR 53.249(a)(5))
- Dispose of termination inventory.
The contractor must dispose of termination inventory within 120 days, unless otherwise negotiated with the TCO. The contractor must also properly report and coordinate with the Government plant clearance officer (PLCO) in reporting and coding inventory.
After the settlement proposal is submitted, the TCO will examine each associated subcontract settlement to determine if subcontract terminations were necessary because of the termination of the prime contract. The TCO will also determine if the contractor’s settlement proposal was developed objectively and reasonably, the associated proposed prices are fair and reasonable, and the proposed prices are allocable to the terminated portion of the contract.
In considering the reasonableness of any associated subcontract settlement, the TCO will generally be guided by the provisions relating to the settlement of prime contracts and will comply with any applicable requirements of FAR 49.1071, Audit of Prime Contract Settlement Proposals and Subcontract Settlements, and FAR 49.1111, Review of Proposed Settlement, relating to accounting and other reviews. After the examination, the TCO will notify the contractor in writing of approval, ratification, or the reasons for disapproval of the contemplated settlement proposal.
As shown below, the FAR contains numerous termination clauses that apply to specific contract types2:
- 52.249-1: Termination for Convenience of the Government (Fixed-Price) (Short Form)
- 52.249-2: Termination for Convenience of the Government (Fixed-Price)
- 52.249-3: Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements)
- 52.249-4: Termination for Convenience of the Government (Services) (Short Form)
- 52.249-5: Termination for Convenience of the Government (Educational and Other Nonprofit Institutions)
- 52.249-6: Termination (Cost-Reimbursement)
- 52.249-7: Termination (Fixed-Price Architect-Engineer)
- 52.249-8: Default (Fixed-Price Supply and Service)
- 52.249-9: Default (Fixed-Price Research and Development)
- 52.249-10: Default (Fixed-Price Construction)
- 52.249-12: Termination (Personal Services)
2FAR Clauses 52.249-1 through 52.249-12
Related services
-
InsightFederal contractors should prepare now for a government shutdownRichard MeeneWith the current political climate, anything is possible; including a government shutdown. Federal contractors should be preparing for a shutdown now. Learn more.
-
Insight2023 GAUGE Report: Lead by ForecastingOur 2023 GAUGE Report includes tips, techniques, and tools to help enable GovCon companies to produce various types of forecasts and benefit from the profound positive impacts.
-
InsightGovernment Impact: Q3 2023An update on CohnReznick's collaboration with federal, state, and local governments.
-
InsightGovernment contractor valuation tracker: H1 2023In this latest Government Contractor Valuation tracker, we take a look at key valuation indicators such as government services composite, S&P 500, mergers and acquisitions, and more. Learn more.
-
On-demandERP: Roadmap for success for government contractorsHear the latest developments and government contracting ERP trends to stay one step ahead of your competition by understanding how properly setting up and managing your ERP solution may affect your operations.